August 6, 2008
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #1 |
Project overview; reasoning for design modifications; draft/initial modified design concepts; overview of possible delivery options; stakeholder outreach; schedule; work with NTTA to determine responsible agency; other issues/next steps. |
|
August 27, 2008
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
City of Lewisville, City of Highland Village, DCTA |
Project overview; stakeholder outreach; schedule; initial/modified concepts; next steps/other issues. |
|
August 28, 2008
Denton County Airport
5000 Airport Road
Denton, TX |
Cities of Denton and Corinth, University of North Texas, and Denton County |
Project overview; stakeholder outreach; schedule; draft/initial/modified concepts; other issues/next steps |
|
September 3, 2008
Lake Dallas City Hall
212 Main St.
Lake Dallas, TX |
Town of Hickory Creek and Cities of Lake Dallas and Corinth |
Project overview; stakeholder outreach; schedule; draft/initial/modified concepts; next steps/other issues. |
|
October 1, 2008
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #2 |
Project overview; refined modified design concepts; stakeholder outreach; schedule; other issues/next steps. |
|
October 15, 2008
URS Corporation
3010 LBJ Freeway, Suite 1300
Dallas, TX
|
DCTA |
Status on operations and funding; reasons for design modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
October 17, 2008
Carrollton City Hall
1945 E. Jackson Rd.
Carrollton, TX
|
City of Carrollton |
Status on operations and funding; reasons for modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
October 17, 2008
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
City of Lewisville |
Status on operations and funding; reasons for modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
October 21, 2008
Denton City Hall
215 E. McKinney Street
Denton, TX |
Denton City Council Mobility Committee |
Status on operations and funding; reasons for design modifications; presentation of project limits; typical sections, mainlanes access locations; stakeholder outreach; open house/public meeting schedule |
|
October 21, 2008
Hickory Creek Town Hall
1075 Ronald Reagan Ave.
Hickory Creek, TX
|
Town of Hickory Creek - City Council |
Status on operations and funding; reasons for modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
October 23, 2008
DCTA
1660 S. Stemmons, Suite 215
Lewisville, TX |
DCTA Board |
Status on operations and funding; reasons for modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
November 3, 2008
Corinth City Hall
3300 Corinth Pkwy.
Corinth, TX
|
City of Corinth – City Council |
Status on operations and funding; reasons for modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
November 10, 2008
UNT Gateway Center
801 North Texas Blvd.
Denton, TX |
Public Meeting – Open to the public |
Open house format |
|
November 5, 2008
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #3 |
Schematic design; environmental documentation; stakeholder outreach; schedule; other issues/next steps. |
|
November 11, 2008
Carrollton City Hall
1945 E. Jackson Rd.
Carrollton, TX |
City of Carrollton – City Council |
Status on operations and funding; reasons for modifications; presentation of project limits, typical sections, and mainlane access locations; stakeholder outreach; open house/public meeting schedule. |
|
November 13, 2008
1197 W. Main St.
Lewisville, TX |
Public Meeting – open to the public |
Open house format. |
|
November 17, 2008
Dr. Pepper Stars Center
12700 North Stemmons Frwy.
Farmers Branch, TX |
Public Meeting – Open to the public |
Open house format |
|
December 3, 2008
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #4 |
Schematic design; environmental documentation; stakeholder outreach; EA/schematic schedule; ROW; other issues/next steps. |
|
February 4, 2009
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #5 |
Schematic design; environmental documentation; stakeholder outreach; EA/schematic schedule; phasing of construction; other issues/next steps. |
|
May 6, 2009
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #6 |
Schematic design; environmental documentation; stakeholder outreach; EA/schematic schedule; phasing of construction; other issues/next steps. |
|
May 14, 2009
UNT Board Room
Hurley Adm. Bldg.
UNT Denton Campus
Denton, TX |
University of North Texas officials |
Schematic design; environmental documentation; stakeholder outreach; EA/schematic schedule; phasing of construction; other issues/next steps |
|
June 16, 2009
Carrollton City Hall
1945 E. Jackson Rd.
Carrollton, TX |
Stakeholder Work Group #7 |
Schematic design; overview of project financing and delivery options; outcome of state legislative session; construction financing and phasing plan. |
|
June 16, 2009
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #8 |
Schematic design; overview of project financing and delivery options; outcome of state legislative session; construction financing and phasing plan. |
|
June 17, 2009
Lake Dallas City Hall
212 Main Street
Lake Dallas, 75065 |
Stakeholder Work Group #9 |
Schematic design; overview of project financing and delivery options; outcome of state legislative session; construction financing and phasing plan. |
|
June 17, 2009
Denton Civic Center
321 E. McKinney
Denton, Texas 76201 |
Stakeholder Work Group #10 |
Schematic design; overview of project financing and delivery options; outcome of state legislative session; construction financing and phasing plan. |
|
August 8, 2009
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #11 |
Schematic design; overview of project financing and delivery options; outcome of state legislative session; construction financing and phasing plan. |
|
August 19, 2009
Lewisville City Hall
151 W. Church St.
Lewisville, TX |
Stakeholder Work Group #11
(elected officials briefing) |
Schematic design; overview of project financing and delivery options; outcome of state legislative session; construction financing and phasing plan |