Schedule (as of June 2010)
October 28, 2009
Received FHWA Approval of Schematics for All Three Segments of IH 35E
September-October, 2010
Conduct Public Hearings*
January-February, 2011
Anticipate Environmental Clearance from FHWA*
February, 2011
Right of Way Mapping/Acquisition**
Early Project Design**
2013-2014
Early Project Construction May Begin**
*Tentative, Subject to FHWA Review and Approval
**Tentative, Subject to the Availability of Funding