Schedule
Schedule (as of January 2012)
October 28, 2009
Received Federal Highway Administration (FHWA) Approval of Schematics for All Three Segments of IH 35E.
January 28, 2011
Received Environmental Clearance from FHWA for IH35E Middle (President George Bush Turnpike to FM2181).
September 27, 2011
Conduct Public Hearings for IH35E South (IH 635 to PGBT) segment.*
October 20, 2011
Conduct Public Hearings for IH35E North (FM 2181 to US 380) segment.*
December 28, 2011
Received Environmental Clearance from FHWA for IH35E South (IH635 to President George Bush Turnpike).
January 2012
Anticipate Environmental Clearance from FHWA for IH35E North segment.*
February, 2011
Right of Way Mapping/Acquisition**
Early Project Design**
2013-2014
Early Project Construction May Begin**
*Tentative, Subject to FHWA Review and Approval
**Tentative, Subject to Environmental Clearance and the Availability of Funding